Under the Bolshoy Stroginsky backwater, tunnel boring has begun between the metro stations “Serebryany Bor” and “Strogino”

Under the Bolshoy Stroginsky backwater, tunnel boring has begun between the metro stations “Serebryany Bor” and “Strogino”

Published on: 2026-08-18

Source: Moscow Government – Правительства Москвы –

An important disclaimer is at the bottom of this article.

The tunnel boring machine (TBM) “Liliya” has started moving under the Bolshoy Stroginsky backwater. It is tunneling the section of the Rublyovo-Arkhangelskaya metro line between the “Serebryany Bor” and “Strogino” stations. This was reported by the Deputy Mayor of Moscow for Urban Policy and Construction. Vladimir Efimov.

“The 10-meter giant shield ‘Liliya’ is engaged in the construction of the Rublyovo-Arkhangelskaya metro line tunnel section between the ‘Serebryany Bor’ and ‘Strogino’ stations. It is working under complex hydrogeological conditions. In total, it will cover about 3.34 kilometers, of which over 1.8 kilometers are under water bodies. The shield has already passed under the Moskva River and has begun work under the Bolshoy Stroginsky backwater. Excavation beneath the water body is carried out strictly in accordance with the design profile. From the top of the tunnel to the bottom, the depth consists of no less than 23.5 meters of soil, and the natural water thickness does not exceed 9.5 meters,” noted Vladimir Efimov.

The soils along the path of the EPB shield are heterogeneous: sand and clay alternate with gravel and dense limestone. Such variations create additional engineering challenges. Precise adjustment of the shield’s technological modes allows overcoming them.

The TBM “Lily” began tunneling in January. Considering the complex hydrogeological conditions at the site, a set of preventive and protective measures has been implemented. In particular, a special emergency action protocol has been developed, which provides for rapid stabilization and reliable waterproofing of the tunnel face in case of excess water. An extended emergency supply of materials and equipment is also constantly maintained on the construction site. There are 220 specialists involved in the section.

The Moscow construction quality standard is ensured by the systematic work of the experts of “Kontrol Moskvy.”

“The construction of the Rublevo-Arkhangelsk line transit tunnels is under control

Moscow State Construction Supervision. The first on-site inspection has already taken place at this section. The inspectors paid special attention to the initial injection of the solution, the quality of the contact between the lining and the ground, and the installation of the highly precise reinforced concrete lining blocks of the tunnel — on which its tightness depends. The next control and supervisory event with the participation of the staff of the subordinate Center for Expertise, Research, and Testing in Construction to conduct a set of laboratory and instrumental inspections of structures and materials is planned for September of this year,” said the chairman of Mosgosstroynadzor. Anton Slobodchikov.

The length of the Rublyovo-Arkhangelskaya line will exceed 27 kilometers. It will include 12 stations with transfer points to Moscow Central Circle, Solntsevskaya, Filevskaya, and Arbatsko-Pokrovskaya The Large Circle Line subway.

Earlier, Sergey Sobyanin instructed to accelerate the pace of construction Rublyovo-Arkhangelskaya metro line. The Mayor of Moscow also spoke about the construction inclined run at the future Dostoevskaya station of the Circle Line of the metro.

To find out how the capital has changed over the past years, what initiatives aimed at making residents’ lives even more comfortable are currently being implemented, and what awaits Moscow and its inhabitants in the near future, you can explore the large-scale special project on the portal mos.ru, dedicated to the development of key areas of the city. These include transport, industry, healthcare, education, sports, and the construction sector.

Project “Transport” It will be interesting for everyone who wants to learn about the main stages of development in this field, support for electric transport, and the development of the route network.